Roads 2024: Pavement Management Program

Share Roads 2024: Pavement Management Program on Facebook Share Roads 2024: Pavement Management Program on Twitter Share Roads 2024: Pavement Management Program on Linkedin Email Roads 2024: Pavement Management Program link

Consultation has concluded

road restructuring with trucks applying asphalt  to roads.


Each year, the Engineering and Construction Section of the Transportation and Public Works Department delivers Pavement Management and Capital Works construction programs to renew and improve infrastructure across Halton Hills. Pavement Management has been an annual local resurfacing program since 2003.

Starting in the spring of 2024, select streets will benefit from road resurfacing, where needed. The work will be managed and administered by the Engineering and Construction Section, Transportation and Public Works Department.

Project Summary by Street:






Draper Street, George Street to James Street Resurfacing

Mill (remove) top asphalt lift, base asphalt repairs as required. Repave asphalt full width of road. Curb and sidewalk repairs in pre-identified areas and storm sewer repairs. Restoration of driveways (full width to the damaged limit), all damaged grassed areas with topsoil and sod.



Evans Place, Mary Street to West End – Resurfacing

Mill (remove) top asphalt lift, base asphalt repairs as required. Subdrain installation. Repave asphalt full width of road. Curb and sidewalk repairs in pre-identified areas. Restoration of driveways (full driveway boulevards), all damaged grassed areas with topsoil and sod.



James Young Drive, Barber Drive to Argyll Road Resurfacing

Mill (remove) top asphalt lift, base asphalt repairs as required. Repave asphalt full width of road. Curb and sidewalk repairs in pre-identified areas. Restoration of driveways (full driveway boulevards or full width to the damaged limit), all damaged grassed areas with topsoil and sod.



Lorne Street, Charles Street to Draper Street Resurfacing

Full depth asphalt removal, curb and sidewalk repairs in pre-identified areas, storm sewer repairs and full width asphalt resurfacing. Restoration of driveways (full width to the damaged limit) all damaged grassed areas with topsoil and sod.



Mary Street, Princess Anne Drive to Cleaveholm Drive
Resurfacing

Mill (remove) top asphalt lift, base asphalt repairs as required. Repave asphalt full width of road. Curb and sidewalk repairs in pre-identified areas, storm sewer repairs and full width asphalt resurfacing. Restoration of driveways (full driveway boulevards) all damaged grassed areas with topsoil and sod.



McGilvray Crescent, Delrex Boulevard to McGilvray Crescent
Resurfacing

Mill (remove) top asphalt lift, base asphalt repairs as required. Repave asphalt full width of road. Curb and sidewalk repairs in pre-identified areas and full width asphalt resurfacing. Restoration of driveways (full driveway boulevards) all damaged grassed areas with topsoil and sod.



Moultrey Crescent, Duncan Drive to
Duncan Drive

Resurfacing

Mill (remove) top asphalt lift, base asphalt repairs as required. Repave asphalt full width of road. Curb and sidewalk repairs in pre-identified areas, storm sewer repairs and full width asphalt resurfacing. Restoration of driveways (full driveway boulevards) all damaged grassed areas with topsoil and sod.



Smith Drive, Mountainview Road S to
Barber Drive
Resurfacing

Mill (remove) top asphalt lift, base asphalt repairs as required. Repave asphalt full width of road. Curb and sidewalk repairs in pre-identified areas and full width asphalt resurfacing. Restoration of driveways (full driveway boulevards or full width to the damaged limit) all damaged grassed areas with topsoil and sod.



William Street, Charles Street to Market –
Minor Reconstruction

Full depth asphalt removal, addition of mountable curb and full width asphalt resurfacing. Restoration of driveways (full driveway boulevards or full width to the damaged limit) all damaged grassed areas with topsoil and sod.



Harold Street, Princess Anne Drive to End Resurfacing

Mill (remove) top asphalt lift, base asphalt repairs as required. Repave asphalt full width of road. Curb and sidewalk repairs in pre-identified areas, storm sewer repairs and full width asphalt resurfacing. Restoration of driveways (full driveway boulevards) all damaged grassed areas with topsoil and sod.



Fourth Line, Highway 7 to 1.2 km south Resurfacing

Cold-in-place asphalt stabilization, pave asphalt full width of road, and re-establish gravel shoulders. Restoration of driveways (full width to the damaged limit) all damaged grassed areas with topsoil and sod or seed.





Each year, the Engineering and Construction Section of the Transportation and Public Works Department delivers Pavement Management and Capital Works construction programs to renew and improve infrastructure across Halton Hills. Pavement Management has been an annual local resurfacing program since 2003.

Starting in the spring of 2024, select streets will benefit from road resurfacing, where needed. The work will be managed and administered by the Engineering and Construction Section, Transportation and Public Works Department.

Project Summary by Street:






Draper Street, George Street to James Street Resurfacing

Mill (remove) top asphalt lift, base asphalt repairs as required. Repave asphalt full width of road. Curb and sidewalk repairs in pre-identified areas and storm sewer repairs. Restoration of driveways (full width to the damaged limit), all damaged grassed areas with topsoil and sod.



Evans Place, Mary Street to West End – Resurfacing

Mill (remove) top asphalt lift, base asphalt repairs as required. Subdrain installation. Repave asphalt full width of road. Curb and sidewalk repairs in pre-identified areas. Restoration of driveways (full driveway boulevards), all damaged grassed areas with topsoil and sod.



James Young Drive, Barber Drive to Argyll Road Resurfacing

Mill (remove) top asphalt lift, base asphalt repairs as required. Repave asphalt full width of road. Curb and sidewalk repairs in pre-identified areas. Restoration of driveways (full driveway boulevards or full width to the damaged limit), all damaged grassed areas with topsoil and sod.



Lorne Street, Charles Street to Draper Street Resurfacing

Full depth asphalt removal, curb and sidewalk repairs in pre-identified areas, storm sewer repairs and full width asphalt resurfacing. Restoration of driveways (full width to the damaged limit) all damaged grassed areas with topsoil and sod.



Mary Street, Princess Anne Drive to Cleaveholm Drive
Resurfacing

Mill (remove) top asphalt lift, base asphalt repairs as required. Repave asphalt full width of road. Curb and sidewalk repairs in pre-identified areas, storm sewer repairs and full width asphalt resurfacing. Restoration of driveways (full driveway boulevards) all damaged grassed areas with topsoil and sod.



McGilvray Crescent, Delrex Boulevard to McGilvray Crescent
Resurfacing

Mill (remove) top asphalt lift, base asphalt repairs as required. Repave asphalt full width of road. Curb and sidewalk repairs in pre-identified areas and full width asphalt resurfacing. Restoration of driveways (full driveway boulevards) all damaged grassed areas with topsoil and sod.



Moultrey Crescent, Duncan Drive to
Duncan Drive

Resurfacing

Mill (remove) top asphalt lift, base asphalt repairs as required. Repave asphalt full width of road. Curb and sidewalk repairs in pre-identified areas, storm sewer repairs and full width asphalt resurfacing. Restoration of driveways (full driveway boulevards) all damaged grassed areas with topsoil and sod.



Smith Drive, Mountainview Road S to
Barber Drive
Resurfacing

Mill (remove) top asphalt lift, base asphalt repairs as required. Repave asphalt full width of road. Curb and sidewalk repairs in pre-identified areas and full width asphalt resurfacing. Restoration of driveways (full driveway boulevards or full width to the damaged limit) all damaged grassed areas with topsoil and sod.



William Street, Charles Street to Market –
Minor Reconstruction

Full depth asphalt removal, addition of mountable curb and full width asphalt resurfacing. Restoration of driveways (full driveway boulevards or full width to the damaged limit) all damaged grassed areas with topsoil and sod.



Harold Street, Princess Anne Drive to End Resurfacing

Mill (remove) top asphalt lift, base asphalt repairs as required. Repave asphalt full width of road. Curb and sidewalk repairs in pre-identified areas, storm sewer repairs and full width asphalt resurfacing. Restoration of driveways (full driveway boulevards) all damaged grassed areas with topsoil and sod.



Fourth Line, Highway 7 to 1.2 km south Resurfacing

Cold-in-place asphalt stabilization, pave asphalt full width of road, and re-establish gravel shoulders. Restoration of driveways (full width to the damaged limit) all damaged grassed areas with topsoil and sod or seed.




Consultation has concluded

Ask Town staff about roads resurfacing in Halton Hills. Your question(s) will be answered in five business days.



  • Share Hello, Inquiring about resurfacing of Glen Lawson to Churchill Rd S and Third Line in Acton. The condition of these roads has been unsafe with many potholes for several years. Thank you, Lauren on Facebook Share Hello, Inquiring about resurfacing of Glen Lawson to Churchill Rd S and Third Line in Acton. The condition of these roads has been unsafe with many potholes for several years. Thank you, Lauren on Twitter Share Hello, Inquiring about resurfacing of Glen Lawson to Churchill Rd S and Third Line in Acton. The condition of these roads has been unsafe with many potholes for several years. Thank you, Lauren on Linkedin Email Hello, Inquiring about resurfacing of Glen Lawson to Churchill Rd S and Third Line in Acton. The condition of these roads has been unsafe with many potholes for several years. Thank you, Lauren link

    Hello, Inquiring about resurfacing of Glen Lawson to Churchill Rd S and Third Line in Acton. The condition of these roads has been unsafe with many potholes for several years. Thank you, Lauren

    LaurenAshley asked 10 months ago

    Thank you for your inquiry.

     Glen Lawson is in the current approved budget and the design work is underway, construction is planned for 2025.

    Third Line is not in the current budget, every five years a review of the condition of the Town’s roads is conducted, priorities are then reviewed during our annual budget process approved and endorsed by Council.

    Regarding the current condition, we will pass on the concerns regarding the potholes to our Public Works team for review. 

  • Share Will we have to park elsewhere instead of our driveways until everything is completed? on Facebook Share Will we have to park elsewhere instead of our driveways until everything is completed? on Twitter Share Will we have to park elsewhere instead of our driveways until everything is completed? on Linkedin Email Will we have to park elsewhere instead of our driveways until everything is completed? link

    Will we have to park elsewhere instead of our driveways until everything is completed?

    M.Hans asked 10 months ago

    Thank you for your inquiry.

    The roads will be open and resident driveways accessible most of the time.  There are specific impacts to properties depending on what was identified through our pre-engineering review.  The most significant impact is when curb or sidewalk is identified to be replaced across your driveway, at that time you will receive notice and will be out of your driveway during preparation, pour and to allow for curing.

    If you have further questions specific to your location, please reach out to me directly at terih@haltonhills.ca, thank you. 

  • Share I'm not seeing any Acton streets on this list. on Facebook Share I'm not seeing any Acton streets on this list. on Twitter Share I'm not seeing any Acton streets on this list. on Linkedin Email I'm not seeing any Acton streets on this list. link

    I'm not seeing any Acton streets on this list.

    Donnie Mack asked 10 months ago

    Thank you for your inquiry.

    For 2024 there are no identified resurfacing locations in Acton in our Capital Budget.

    Our future years resurfacing has not yet been determined as the condition review data is anticipated this year.  Every five years, a review of the condition of the Town’s roads is conducted, priorities are then reviewed during our annual budget process approved and endorsed by Council.